CONSTRUCTION UPDATES DECEMBER 2016

VinaCapital Danang Resort Ltd would like to send you the latest construction update for VinaLiving’s latest residential project in Danang ‘The Ocean Estates’: –

  • REC Club: The Developer completed upgrading existing facilities at REC Club including the pool area, barbecue, sales gallery to serve customers visiting the project.
  • Infrastructure: Basic infrastructures at project including internal roads, electricity, lighting, water supply, drainage, guard house, the lake landscape have now been completed. As planned, the remaining infrastructure will be completed in Q4 2017
  • The site preparation and villas construction:
  1. Site Preparation: 100% completed
  2. Villa Construction:
  • The contractor has mobilized onsite with construction of a number of home foundations now underway.
  • Foundation for the first 4 villas expected to complete in January 2017
  • Delivery: Scheduled for Q4 2017

On this occasion nearing the start of the Year of Rooster, VinaCapital Danang Resort Ltd wishes you all a Happy New Year and great prosperity for 2017.