CONSTRUCTION UPDATES AUGUST 2018

Dear Valued Customers,

VinaCapital Danang Resort Ltd would like to send you the latest construction update for VinaLiving’s latest luxury residential housing community in Danang known as ‘The Ocean Estates’:

  • Villa construction progress to 31st August 2018
  • All villas have been completed and now hand over to the Customers. Details are below:
  • Row A & B Villas: All villas handed over
  • Row C Villas: Handed over 6 (out of 6) villas. Phase 2 including C1 – C4 are under construction and schedule to hand over in Quarter 4/2018.

Villa C1:

  • External plastering and roof tile completed
  • Internal gypsumboard ceiling is in progress
  • Gymsumboard ceiling installation is in progress.

Villa C2:

  • External painting work is in progress
  • Internal ID work is on going
  • Pool stone tiling completed

Villa C3:

  • External plastering is in progress
  • MEP installation and plastering in 1st floor in progress

Villa C4:

  • External plastering is in progress
  • Roof tiling completed

 

  • Row D Villas: Handed over 3 (out of 7) villas. The remained villas are ready to hand over.

 